E2001/02/03 ringsted-fehmarn banen,
civil works.
The contract covers the design, planning and execution of civil works. This includes earthworks and works in regard to sub-ballast, ballast, storm water drainage, structures etc. in connection with the upgrade of the railway line between Ringsted and Fehmarn:
The contract has been divided into 3 lots:
E 2001 - Ringsted-Vordingborg
Tender package E 2001 covers the execution of civil works located in the geographic area of southern Zealand. The rail line is currently a single-track rail line and the scope of works includes amogst others the following main elements:
-
Approx. 2,3 km single track rail embankment and ballast incl. drainage
-
Approx. 10,4 km double track rail embankment and ballast incl. drainage
-
3 fauna and/ or water passages
-
3 bridge structures to be demolished and roads to be closed
-
Approx. 13 km of noise barriers along track
key facts.
Client. International Contractor
Value. DKK 980.000.000
Services. Tender Management,
Engineering, Quantity
Survey
Scope. Bridge Works, Road Works,
Civil Works
Location. Denmark
Year. 2014
E2002 - Falster
This tender package covers the execution of civil works on the Island of Falster. The rail line is currently a single-track rail line, and the scope of work generally includes adding an additional track as well as replacing the ballast and the sub-ballast of the existing track. The scope of works includes amongst otehrs the following main components:
-
Approx. 15.000 m3 soft soil replacement
-
Approx. 3 km single track rail embankment and ballast incl. drainage
-
Approx. 19 km double track rail embankment and ballast incl. drainage
-
Approx. 38 water passages
-
2 pedestrian tunnels with partial renewing of waterproofing under the tracks
E2003 - Lolland
The civil works within the tender package E 2003 are to be executed on the Island of Lolland. The rail line is currently a single-track rail line, and the scope of work generally includes adding an additional track as well as replacing the ballast and the sub-ballast of the existing track. Amongst others, the following main works are included:
-
Approx. 124.000 m3 soft soil replacement
-
Approx. 4 km single track rail embankment and ballast incl. drainage
-
Approx. 31 km double track rail embankment and ballast incl. drainage