As the third part delivery to the project "Fjord Link Frederikssund," tendered by Vejdirektoratet, NOROQ has delivered and mounted two precast square tunnels for "OP Skibbyvej North and OP Skibbyvej South".
The underpasses under Skibbyvej are for cyclists and pedestrians.
Location: DK-4050 Skibby
OP skibbyvej north and south
Anker 1

key facts.
Skibbyvej North
Skibbyvej south
System. Square Tunnel Square Tunnel
Total Length. 33,3 m 31,0 m
Clearance Height. 3,0 m 2,9 m
Clearance Width. 4,5 m 4,5 m